10 June 2025

Tramway Track Renovation at the Intersection of Prince Volodymyr the Great Avenue and Academician Zabolotny Street

The renovation of the tramway track has commenced at the intersection of Prince Volodymyr the Great Avenue and Academician Zabolotny Street.

The first phase of the renovation was successfully completed, lasting from May 16 to June 2, covering a 50-meter segment of the single-track line.

The second phase has now begun, which involves renovating an additional 100 meters of tramway track. This phase is scheduled from June 3 to June 26. Following this, two more phases are planned, including a major renovation with partial replacement of the curved section.

The total length of the renovation area is 250 meters. Work is being carried out in stages, with partial restrictions on vehicle traffic.